THAT THE INFRASTRUCTURE AND PUBLIC WORKS COMMITTEE RECOMMENDS TO COUNCIL
THAT COUNCIL:
1. Notes the Capital Works Program Update for May 2026 as contained within this report and Attachment A to Item 7.3 on the Agenda for the meeting of the Infrastructure and Public Works Committee held on 16 June 2026.
THAT THE INFRASTRUCTURE AND PUBLIC WORKS COMMITTEE RECOMMENDS TO COUNCIL
THAT COUNCIL
1. Approves to progress Stage 2 streetscape concept to detailed design, which will incorporate community feedback to further refine key design elements.
2. Notes the community engagement process and feedback on the proposed concept design, as contained in Attachment A to Item 7.4 on the Agenda for the meeting of the Infrastructure and Public Works Committee held on 16 June 2026.
3. Notes additional information regarding promotional and outreach activities to encourage community participation for Stage 2 streetscape upgrade, as contained in Attachment B to Item 7.4 on the Agenda for the meeting of the Infrastructure and Public Works Committee held on 16 June 2026.
4. Notes that a project update will be provided to Council once 70% design and a construction staging plan incorporating community feedback are completed for Stage 2 streetscape upgrade.
5. Endorses speed limit of 40km/h on Melbourne Street to be implemented in conjunction with Stage 1 wombat crossings, which is expected to be completed by 30 September 2026.
Undertaking - Melbourne Street Revitalisation - Community Consultation Summary
In response to a query from Councillor Siebentritt, an undertaking was given to look at early implementation of piloting flexible parking spaces.